Gas furnace startup / commissioning

Startup

All guides
Startup· Moderate 45–60 min

Post-install verification of a residential 80% or 90%+ furnace.

Tools
Combustion analyzer · Manometer · Multimeter
1

Verify gas pressure

Static 5–7" WC NG (11–14" LP). Manifold to nameplate — typically 3.5" NG / 10" LP.

2

Clock the meter

Confirm firing rate matches nameplate BTU input.

3

Check combustion

CO stack <100 ppm air-free; O2 6–9%. Adjust airflow or gas as needed.

4

Measure temperature rise

Return-to-supply rise within nameplate window (typically 35–65°F).

5

Static pressure

Total ESP ≤0.5" WC; adjust blower tap or duct.